Cleaver Brooks Electric Boiler - HSB 750-137 Quarterly Maintenance

MaintainX
04/26/2021

Cleaver Brooks Electric Boiler - HSB 750-137 Quarterly Maintenance

    Warning: Lockout and disconnect the main power before tightening the main supply lugs in order to avoid the hazard of electrical shock, which could result in serious personal injury or death.

    Tighten the main supply lugs every 24 hours during the first week of operation.

    Caution: When checking the element terminal connections, use a wrench on both nuts to avoid twisting the terminal stud and damaging the equipment.

    If all elements have been operating normally and each element bank draws its rated current or amperage, where no further element tests are necessary.

Source: Cleaver Brooks

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.