Back

Mobi Site Inspection Guide.

This procedure should be followed so as to accurately identify any potential failures at different sections of the sites and should be done at least once in every two weeks.
Give Power
03/03/2025

Mobi Site Inspection Guide.

This procedure should be followed so as to accurately identify any potential failures at different sections of the sites and should be done at least once in every two weeks.
Procedure Max Score: 50

    Date

    Site Name

    Borehole Pump VFD

    Media Filters

    Raw water pump

    Micron Filters

    Main Spectra Controls

    Note and alarms that are currently deactivated.

    KB Genesis Controller

    Use the power and status LEDs

    Pearson Pumps

    Spectra Sensors

    Inverters

    Powerwalls

    Generation and Distribution Panel

    Product and Raw Water Tanks.

    Network Equipment

    Distribution pumps & VFD

    Chemical Dosing Pumps

    Plumbing Network

    Soakpit, Injection Well & Washrooms

    Metallic Structures ,Walls & Others

Source: Give Power (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.