Daily checklists ensure tasks we set out to do during the day will be completed correctly by clearly outlining the steps we must not miss. Speed and efficiency help time management, and task management empowers teams to be productive.
SV - Labs
07/24/2024

RPA1 - CIL - Daily Checklist

Procedure Max Score: 34

    Clean the machine exterior using a dry cloth

    Manual - Cloth

    • Pass
    • Flag
    • Fail

    Inspect spreader conveyor belt for any wear and tear

    Visual - N/A

    • Pass
    • Flag
    • Fail

    Inspect oufeed conveyor belt for any wear and tear

    Visual - N/A

    • Pass
    • Flag
    • Fail

    Clean precompression and Eject tooling pins

    Manual - Air gun, cloth & brush

    • Pass
    • Flag
    • Fail

    Ensure all emergencies stop buttons are operational by running the machine and pressing EMO buttons

    Manual - N/A

    • Pass
    • Flag
    • Fail

    Clean the upper and lower tooling on all stations

    Manual - Air gun, cloth & brush

    • Pass
    • Flag
    • Fail

    Clean the material adjust station

    Manual - Air gun & Cloth

    • Pass
    • Flag
    • Fail

    Clean the dust from the electrical enclosure

    Manual - Vacuum Cleaner or dry cloth

    • Pass
    • Flag
    • Fail

    Ensure that the back panel is closed

    Visual - N/A

    • Pass
    • Flag
    • Fail

    Lubricate the gear on the spreader

    Manual - WD40

    • Pass
    • Flag
    • Fail

    Inspect all pneumatic cylinders for air leaks, use ladder to inspect top of machine

    Visual - Hand

    • Pass
    • Flag
    • Fail

    Inspect the frame for any cracks

    Visual - N/A

    • Pass
    • Flag
    • Fail

    Inspect the gear on the outfeed conveyor and lubricate the gears using high temp grease

    Manual - Grease gun

    • Pass
    • Flag
    • Fail

    Lubricate the bearing on the infeed conveyor using high temp grease

    Manual - Grease gun

    • Pass
    • Flag
    • Fail

    Lubricate the bearing on the outfeed conveyor using high temp grease

    Manual - Grease gun

    • Pass
    • Flag
    • Fail

    Run the machine and make sure no abnormalities are observed

    Manual - Hand

    • Pass
    • Flag
    • Fail

    Inspect WIP trays and dispose any not acceptable trays. Mark fail if there was defective trays and type number of trays.

    Visual - Hand

    • 1721780896259-62f502f9-1723-4548-982a-8b102233235b_1.jpg
    • Pass
    • Flag
    • Fail

    Sign off on the inspection

    Click here to sign
Source: SV - Labs (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.