Follow the LOTO procedures below to ensure the proper graceport validation.
24P DC Columbus - Cintas
03/05/2024

Graceport Validations

Follow the LOTO procedures below to ensure the proper graceport validation.

    *** LOTO Confirmation Statement - DO NOT EDIT/REMOVE ***

    All hazardous energy has been isolated using LOTO procedures?

    All potential stored or residual energy has been relieved, disconnected, restrained, lowered, and/or otherwise rendered safe?

    Please upload all Graceport Validations

    Add or drag pictures

    Any required changes identified? - Create a corrective work order

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FLAG,FAIL]"

    Any required changes identified? - Create a corrective work order

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FLAG,FAIL]"

    Any required changes identified? - Create a corrective work order

    • Pass
    • Flag
    • Fail

    Any additional comments? If more than 3 items identified in report for work that needs to be completed, please make additional WO.

Source: 24P DC Columbus - Cintas (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.