Use the guidelines below for the inspection of your oxidizer control panel.
Weekend Inspections Night Shift
Use the guidelines below for the inspection of your oxidizer control panel.
Date & Time
Planned work & Breakdowns
Ammeter Readings
Carry our reading and log in Folder
Is Log is up to date
Oxidiser control panel
Carry out the following Inspections on the assets listed:
Test sounder and strobe for operation, pressing the button located on the front of the panel.
Chlorine units
Carry out the following Inspections on the assets listed:
B1 Sump - Removing the stir bar Press the MENU key, then press the down ARROW key until the MAINT menu appears. Press ENTER. Remove the plug from the top hole of the colorimeter. 3 Colorimeter assembly. Gently insert a straightened paper clip into the hole at the top of the colorimeter and slowly pull out the stir bar. Insert a wooden or paper cotton-tipped swab* into the opening and move it up and down with a gentle scrubbing action, cleaning the interior surfaces of the colorimeter cell. Clean the stir ba
Water Plant - Removing the stir bar Press the MENU key, then press the down ARROW key until the MAINT menu appears. Press ENTER. Remove the plug from the top hole of the colorimeter. 3 Colorimeter assembly. Gently insert a straightened paper clip into the hole at the top of the colorimeter and slowly pull out the stir bar. Insert a wooden or paper cotton-tipped swab* into the opening and move it up and down with a gentle scrubbing action, cleaning the interior surfaces of the colorimeter cell. Clean the st
Thru air dryer exhaust VSD’s fan and filters
Carry out the following Inspections on the assets listed:
TAD 1 – Clean or replace cooling fan filter.
TAD 2 – Clean or replace cooling fan filter.
TAD 3 – Clean or replace cooling fan filter.
Ensure Both Room Fans are in Operation
Beilomatic
Carry out the following Inspections on the assets listed:
Change filters as when required and clean to put back in stores
Empty oil drip trays as necessary.
Sump alarm tests
Carry out the following Inspections on the assets listed:
Basement – Test sump alarm and ensure fully operational
Basement Pit – Test sump alarm and ensure fully operational
Old Mill sump – Test sump alarm and ensure fully operational.
Corrective Action
Were any checks incomplete?
if the answer is "oneOf [Yes]"
If Not Why Not
Is any follow up work required?
if the answer is "oneOf [Yes]"
Remarks
Are all guards and their fixing in place, secure and operational? (If NO, state reason)
if the answer is "oneOf [No]"
Remarks
Any Other Comment
Source: Ahlstrom (Community Member)