PM Solenoid - 250-300 Core Staking
Use this procedure for the monthly preventive maintenance of your machine's core-C frame assembly and inspection of it specific components.
PM Solenoid - 250-300 Core Staking
Use this procedure for the monthly preventive maintenance of your machine's core-C frame assembly and inspection of it specific components.
DISCONNECT ENERGY, INSTALL THE TAGOUT LOCK !!!
A GOOD JOB IS CRUCIAL PART OF YOUR PROFESSIONAL IMPROVEMENT/GROW
PLEASE MAKE SURE TO FOLLOW THIS MAINTENANCE RUTINE/INSTRUCTION
1. Core – C-Frame ASSEMBLY
1.1- Items to check and correct if needed at the station:
-Trays
-Servo sensors:
- Servo controller:
-Cables and cylinders/part presence sensors:
-Shock absorbers and mechanical stops:
-Valves:
1.8 Check cylinders alignment (vertical and horizontal axes). Adjust if needed:
1.9 Check Air Nozzle System and clean filter.
Inspect the correct functionality of the following Items:
-Interlock on door :
-E-Stop Button:
-Additional notes:
Signature:
Click here to sign
Source: SOPT Maintenance (Community Member)